Multnomal County - Portland Oregon - 2016 - 2021

Central Courthouse

LEEDv4 Gold with Green Canary — 460,000 SF

560K SF

Size

LEED Gold

Cert

2021

Year

EcoREAL Role: LEED Project Administrator (Principal in charge: Summer Fowler)

Summer Fowler led an eco-charrette in pre-design with project stakeholders, architects, engineers, contractors, and facility managers to establish goals, opportunities, and synergies that set the strategic path. Achieved LEED Gold without any additional capital expense by deploying Green Canary's Lean LEED CA tools.

  • Triple-bottom-line strategy assessment: rainwater management, water and energy systems

  • Green Canary deployment with Hoffman Construction to streamline LEED submittals

  • LEED Gold delivered with no capital cost premium